The window & door jambs are installed at this station, along with baseboard, window & door trim, and the interior doors are hung. The ceramic tile backsplash is done here, and the ceramic shower. The tack strip and carpet pad are installed, and tomorrow it will get carpet. At this point in the line the minor drywall repairs are taped and it will move onto the final stage of drywall tomorrow, they touch up any errors.
It starts looking more like a home at this point with all the components coming together. Tomorrow will be the last day on the production line!
No comments:
Post a Comment