Thursday, June 13, 2013

Delivery Day!

Last night I was concerned about the slope of the grade for the house to park on, my dad went to the site and ran a dozer over the slope and made it smooth.  It is great having a dad that can run any type of equipment, and fix anything, my worries about the land went away!


My dad and husband also marked the ground for where the houses should be placed for the crane to be able to maneuver between tomorrow.


As expected it stormed last night for hours, so our ground is very wet.  The home is leaving the factory this morning and going to the site. If the site is too wet, we are going to need to park it in the parking lot next to our house and move it to the specific spot later this afternoon once it has dried out. 

10:45 AM
First half of home was delivered to the site! Bad news site is too wet for the house, so the house is parked in the Church's parking lot to the east of our lot.  Now crossing our fingers that it will dry up enough for the houses to be moved over to the site this evening with the dozer. 

My husband called the guy who is doing the dirt work, he agreed to come out and move the peel the mud. 

12:45
The second half of the home is on the site! They got enough mud cleared off for the house to fit into place.  The truck driver being so gracious also moved the first half onto the site. 



Cross our fingers that we do not receive any more rain and the crane should be fine in the morning!

The contractor is also on site today, building some walls in the basement in preparation for tomorrows set!