Friday, May 17, 2013

Day 3 of Production

Today is wall set and electrical day! Almost all of the walls were set before I got to the factory this morning. It looks totally different going from a flat floor to walls up everywhere! It was awesome to see this morning. 





 
This afternoon I went back to see what had been accomplished, more walls, the electical wires were being ran, and the attic stairs were in! The base cabinets were set in the home, but now wall cabinets were being installed.



 
Afternoon trip to the Factory! Kitchen Cabinets are hung on the wall! Our roof is framed, one half has a ceiling! Moving right along!
 





 
 
 
 
I got a text message from my husband today with pictures of the footers being poured in our basement!
 